Hi Celopeers,I am wondering the PQL statement for Cycle time of the process.For the below process, throughput time is selected. I realized that Cycle time is more than the cumulatives of the first activity throughput time till the end activity

  • March 23, 2022
  • 1 reply
  • 19 views

1 reply

  • Level 0
  • April 18, 2022

Hi Zeliha,

 

The throughput time that You see in the Process Explorer is only showing the direct timeline from one activity to the next one, in other words, it is showing You a variant of Your process where that exact path of activities has been followed and in that order. The cycle time analysis will take in consideration all possible paths and order of executions from start to finish.