Hi all,

 

I have a basic question regarding activity table column configuration. We have the luxury of having start AND end datetimes for each activity. I remember this was possible at some point to specify the date columns as such with the effect that for each activity the duration was calculated and shown in the process explorer (performance view).

 

Is this still possible, and if so, how?

 

Thank you!

Hi @Gregor Scheithauer - I know exactly what you're talking about, but it seems like that feature has been removed from the activity table configuration, which seems odd. I would recommend creating a support ticket with the servicedesk, as they might be able to enable that feature for you.

 

As an alternative - you can create an additional field in your eventlog that will calculate the duration of the activity by utilizing DATEDIFF, and then build that as a KPI in your analysis.